image_pdfimage_print

In case of imminent endangerment of the environment, BALSA GmbH undertakes the projecting and realisation of measures for the protection / remediation of affected properties.

Deutsch Jahrndorf earthworks

Burgenland

Project type:

After the shutdown of the Deutsch Jahrndorf earthworks in 2005, sludge, drainage water from dumps, tyres, packing material, bins containing dangerous materials, building rubble and textile waste were stored on the area. During the period 2006 – 2008, project planning and clearance of the area were executed. Overall, approx. 6.800 tons of waste materials were cleared and transported to external disposal plants.

Assignments of  BALSA by order of the district authorities of Neusiedl:

  • planning earthworks
  • carrying out of tendering and award procedures
  • local supervision of works in progress
  • project management

This project has been completed in January 2008.

Deutsch Jahrndorf earthworks (aerial view)
BALSA GmbH
Prior to waste removal
BALSA GmbH
Cleared up site
BALSA GmbH
Previous
Next

Photo gallery Deutsch Jahrndorf earthworks

BUNDESALTLASTENSANIERUNGSGES.M.B.H.
A-1230 Vienna, Mosetiggasse 1 / 2nd floor

TEL: +43(0)1 90313-0   FAX: +43(0)1 90313-301

copyright BALSA GmbH 2006 – 2019