Completed Projects
-
Contaminated Site N55&56 / Lower Austria
Betongrubenfelder
Subject of Project
The concrete pit fields ("Betongrubenfelder"), which have to be remediated, are situated south-east of the already cleaned up „Fischerdeponie“. They originated before 1945 in the course of gravel exploitation for the construction of concrete fundaments. Up to the seventies, the pits were filled with garbage, construction waste, excavation materials and barrels with various contents (distillation residues, mineral oil products, organic solvents etc.). The containers that were recovered and some of the contaminated excavation material were disposed of. After the installation of a sealing layer approx. 1 m thick, the remaining excavation material was put back and also covered in an upward direction with a sealing layer of approx. 1 m. -
Contaminated Site N55&56 / Lower Austria
Betongrubenfelder
Subject of Project
The concrete pit fields ("Betongrubenfelder"), which have to be remediated, are situated south-east of the already cleaned up „Fischerdeponie“. They originated before 1945 in the course of gravel exploitation for the construction of concrete fundaments. Up to the seventies, the pits were filled with garbage, construction waste, excavation materials and barrels with various contents (distillation residues, mineral oil products, organic solvents etc.). The containers that were recovered and some of the contaminated excavation material were disposed of. After the installation of a sealing layer approx. 1 m thick, the remaining excavation material was put back and also covered in an upward direction with a sealing layer of approx. 1 m.
-
> more
Remediation measures:
- Remediation by so-called soil-suction and cleaning of the contaminated air by sending it through an exhaust air treatment system.
- Operation of the soil-suction equipment for approx. 3 years.
Services provided by BALSA:
Complete realisation and carrying out of remediation measures:
- basic engineering / planning of project filing / detailed planning
- design and carrying out of detailed exploration
- engineering of remediation measures
- carrying out of tendering and award procedures
- all agenda in connection with project management and project steering
Closure of the project: December 2012
-
Burgenland
Donnerskirchen
Subject of Project
The objective of this project is the removal and treatment of illegally deposited waste materials of upper calorific value according to the laws. The materials in question consist of preprocessed municipal and commercial waste, as well as preprocessed waste from construction sites, which were stored in a former warehouse. According to the underlying enforcement ruling, all in all 325.22 t of waste materials were cleared and transported to thermal treatment plants within 2 days.
-
Burgenland
Donnerskirchen
Subject of Project
The objective of this project is the removal and treatment of illegally deposited waste materials of upper calorific value according to the laws. The materials in question consist of preprocessed municipal and commercial waste, as well as preprocessed waste from construction sites, which were stored in a former warehouse. According to the underlying enforcement ruling, all in all 325.22 t of waste materials were cleared and transported to thermal treatment plants within 2 days. -
Burgenland
Donnerskirchen
Subject of Project
The objective of this project is the removal and treatment of illegally deposited waste materials of upper calorific value according to the laws. The materials in question consist of preprocessed municipal and commercial waste, as well as preprocessed waste from construction sites, which were stored in a former warehouse. According to the underlying enforcement ruling, all in all 325.22 t of waste materials were cleared and transported to thermal treatment plants within 2 days.
-
> more
Services provided by BALSA by order of the district authorities of Eisenstadt-Umgebung:
- Planning groundwork
- Carrying out of tendering and award procedures
- Local supervision of works in progress
- Project Management
This project has been completed in March 2009.
-
Burgenland
Erdwerk Deutsch Jahrndorf
Subject of Project
After the shutdown of the "Deutsch Jahrndorf earthworks" in 2005, sludge, drainage water from dumps, tyres, packing material, bins containing dangerous materials, building rubble and textile waste were stored on the area. During the period 2006 – 2008, project planning and clearance of the area were executed. Overall, approx. 6.800 t of waste materials were cleared and transported to external disposal plants.
-
> more
Services provided by BALSA by order of the district authorities of Neusiedl:
- Planning earthworks
- Carrying out of tendering and award procedures
- Local supervision of works in progress
- Project Management
This project has been completed in January 2008.
-
Contaminated Site N1 / Lower Austria
Fischer Deponie
Subject of Project
The area of the Fischer landfill site ("Fischer Deponie") east of Theresienfeld – once used as a gravel pit – was filled with domestic, industrial and commercial waste, oil-contaminated materials and building rubble throughout the 1970s and 1980s. Contrary to the original allocations, non-permitted waste materials were deposited far beyond the borders of the original landfill site – even underneath the upper level of ground water. -
Contaminated Site N1 / Lower Austria
Fischer Deponie
Subject of Project
The area of the Fischer landfill site ("Fischer Deponie") east of Theresienfeld – once used as a gravel pit – was filled with domestic, industrial and commercial waste, oil-contaminated materials and building rubble throughout the 1970s and 1980s. Contrary to the original allocations, non-permitted waste materials were deposited far beyond the borders of the original landfill site – even underneath the upper level of ground water. -
Contaminated Site N1 / Lower Austria
Fischer Deponie
Subject of Project
The area of the Fischer landfill site ("Fischer Deponie") east of Theresienfeld – once used as a gravel pit – was filled with domestic, industrial and commercial waste, oil-contaminated materials and building rubble throughout the 1970s and 1980s. Contrary to the original allocations, non-permitted waste materials were deposited far beyond the borders of the original landfill site – even underneath the upper level of ground water. -
Contaminated Site N1 / Lower Austria
Fischer Deponie
Subject of Project
The area of the Fischer landfill site ("Fischer Deponie") east of Theresienfeld – once used as a gravel pit – was filled with domestic, industrial and commercial waste, oil-contaminated materials and building rubble throughout the 1970s and 1980s. Contrary to the original allocations, non-permitted waste materials were deposited far beyond the borders of the original landfill site – even underneath the upper level of ground water.
-
Contaminated Site N1 / Lower Austria
Fischer Deponie
Subject of Project
The area of the Fischer landfill site ("Fischer Deponie") east of Theresienfeld – once used as a gravel pit – was filled with domestic, industrial and commercial waste, oil-contaminated materials and building rubble throughout the 1970s and 1980s. Contrary to the original allocations, non-permitted waste materials were deposited far beyond the borders of the original landfill site – even underneath the upper level of ground water. -
Contaminated Site N1 / Lower Austria
Fischer Deponie
Subject of Project
The area of the Fischer landfill site ("Fischer Deponie") east of Theresienfeld – once used as a gravel pit – was filled with domestic, industrial and commercial waste, oil-contaminated materials and building rubble throughout the 1970s and 1980s. Contrary to the original allocations, non-permitted waste materials were deposited far beyond the borders of the original landfill site – even underneath the upper level of ground water. -
Contaminated Site N1 / Lower Austria
Fischer Deponie
Subject of Project
The area of the Fischer landfill site ("Fischer Deponie") east of Theresienfeld – once used as a gravel pit – was filled with domestic, industrial and commercial waste, oil-contaminated materials and building rubble throughout the 1970s and 1980s. Contrary to the original allocations, non-permitted waste materials were deposited far beyond the borders of the original landfill site – even underneath the upper level of ground water. -
Contaminated Site N1 / Lower Austria
Fischer Deponie
Subject of Project
The area of the Fischer landfill site ("Fischer Deponie") east of Theresienfeld – once used as a gravel pit – was filled with domestic, industrial and commercial waste, oil-contaminated materials and building rubble throughout the 1970s and 1980s. Contrary to the original allocations, non-permitted waste materials were deposited far beyond the borders of the original landfill site – even underneath the upper level of ground water.
-
> more
In the period of 2001 – 2008, the remediation of the Fischer landfill site was executed by the Republic of Austria, represented by the district authorities of Wiener Neustadt. To that, the complete waste body had to be cleared. The dug out waste materials (mainly domestic waste and contaminated soil, as well as barrels filled with solvent liquids) had to be transported to external treatment plants to be disposed of according to the laws.
Disposal balance:
940,000 t waste / approx. 15,000 containers / 1.1 million t subsoil material
Overall project costs:
approx. € 130 Mio (inkl. VAT)
Services provided by BALSA by order of the district authorities of Wiener Neustadt:
At the beginning of 2005, BALSA was charged with the continuation of the project management.
This project has been completed in January 2008.
-
Contaminated Site ST7 / Styria
Gärtnerei Thianich
Subject of Project
Up to the beginning of the 1980s, the “Gärtnerei Thianich” was located on this plot of land at the east end of the municipality of Zettling. The company´s equipment included a heating house and a mineral oil stock. On the areal of the former heating system, contaminations of the underground were detected. In the 1970s, oil ingresses into the nearby well happened. In 1992, the contaminated subsoil was partially trenched. Part of the contaminated soil was stored on the site wrapped in polyethene sheets. -
Contaminated Site ST7 / Styria
Gärtnerei Thianich
Subject of Project
Up to the beginning of the 1980s, the “Gärtnerei Thianich” was located on this plot of land at the east end of the municipality of Zettling. The company´s equipment included a heating house and a mineral oil stock. On the areal of the former heating system, contaminations of the underground were detected. In the 1970s, oil ingresses into the nearby well happened. In 1992, the contaminated subsoil was partially trenched. Part of the contaminated soil was stored on the site wrapped in polyethene sheets. -
Contaminated Site ST7 / Styria
Gärtnerei Thianich
Subject of Project
Up to the beginning of the 1980s, the “Gärtnerei Thianich” was located on this plot of land at the east end of the municipality of Zettling. The company´s equipment included a heating house and a mineral oil stock. On the areal of the former heating system, contaminations of the underground were detected. In the 1970s, oil ingresses into the nearby well happened. In 1992, the contaminated subsoil was partially trenched. Part of the contaminated soil was stored on the site wrapped in polyethene sheets. -
Contaminated Site ST7 / Styria
Gärtnerei Thianich
Subject of Project
Up to the beginning of the 1980s, the “Gärtnerei Thianich” was located on this plot of land at the east end of the municipality of Zettling. The company´s equipment included a heating house and a mineral oil stock. On the areal of the former heating system, contaminations of the underground were detected. In the 1970s, oil ingresses into the nearby well happened. In 1992, the contaminated subsoil was partially trenched. Part of the contaminated soil was stored on the site wrapped in polyethene sheets. -
Contaminated Site ST7 / Styria
Gärtnerei Thianich
Subject of Project
Up to the beginning of the 1980s, the “Gärtnerei Thianich” was located on this plot of land at the east end of the municipality of Zettling. The company´s equipment included a heating house and a mineral oil stock. On the areal of the former heating system, contaminations of the underground were detected. In the 1970s, oil ingresses into the nearby well happened. In 1992, the contaminated subsoil was partially trenched. Part of the contaminated soil was stored on the site wrapped in polyethene sheets.
-
> more
Remediation measures:
- Disposal of temporarily stored, contaminated excavation materials
- Exploration of subsoil / registration and demarcation of contaminated underground areas
- Clearance of contaminated subsoil (esp. groundwater fluctuation range)
- Disposal of excavation materials
- Backfilling / Recultivation
Services provided by BALSA:
Complete realisation and carrying out of remediation measures:
- Basic engineering / planning of project-filing / detailed planning
- Design and carrying out of detailed exploration
- Engineering of remediation measures
- Carrying out of tendering and award procedures
- All agenda in connection with project management and project steering
Closure of the project: December 2008
-
Tyrol
Going
Subject of Project
The objective of this project is the reconstruction of stabilisation measures after the landslide in Going a.W.K. by refortification of the scarp, including a reinforcement and drainage system. Excavation materials have to be definitively disposed of according to the rules.
-
> more
Services provided by BALSA by order of the district authorities of Kitzbühel:
- Planning groundwork
- Carrying out of tendering and award procedures
This project has been completed in November 2011.
-
Lower Austria
Recycling Point Blumau
Subject of Project
The objective of the project in the municipality of Blumau-Neurisshof was the clearing of all stacks and piles of waste materials which had been illegally deposited from the mounted operational area and from the plant warehouses of a bankrupt company.
During the period 2005 – 2006, approx. 80,000 t of waste materials were cleared and transported to appropriate treatment plants. -
Lower Austria
Recycling Point Blumau
Subject of Project
The objective of the project in the municipality of Blumau-Neurisshof was the clearing of all stacks and piles of waste materials which had been illegally deposited from the mounted operational area and from the plant warehouses of a bankrupt company.
During the period 2005 – 2006, approx. 80,000 t of waste materials were cleared and transported to appropriate treatment plants. -
Lower Austria
Recycling Point Blumau
Subject of Project
The objective of the project in the municipality of Blumau-Neurisshof was the clearing of all stacks and piles of waste materials which had been illegally deposited from the mounted operational area and from the plant warehouses of a bankrupt company.
During the period 2005 – 2006, approx. 80,000 t of waste materials were cleared and transported to appropriate treatment plants.
-
> more
Services provided by BALSA by order of the district authorities of Baden:
- local supervision of works
This project has been completed in March 2006.
-
Burgenland
Reifendeponie Großwarasdorf
Subject of Project
On this plot of land near Oberpullendorf, scrap tyres and shreds were stored over many years without any fortification with regard to the subsoil. During the period 2006 – 2007, the project planning as well as the clearance of the area were handled. Overall, approx. 3.000 t of scrap tyres and shreds, as well as minor quantities of harmful substances, industrial waste and bulky refuse were cleared and transported to various waste treatment and disposal plants. -
Burgenland
Reifendeponie Großwarasdorf
Subject of Project
On this plot of land near Oberpullendorf, scrap tyres and shreds were stored over many years without any fortification with regard to the subsoil. During the period 2006 – 2007, the project planning as well as the clearance of the area were handled. Overall, approx. 3.000 t of scrap tyres and shreds, as well as minor quantities of harmful substances, industrial waste and bulky refuse were cleared and transported to various waste treatment and disposal plants.
-
> more
Services provided by BALSA by order of the district authorities of Oberpullendorf:
- Planning groundwork
- Execution of tendering and award procedures
- Local supervision of works
- Project Management
This project was completed in December 2007.
-
Contaminated Site ST1 / Styria
Teerfabrik Lederer-Mellitzer
Subject of Project
On this areal in the community of Stocking, factory equipment for the production of tar-products was based after World War II. For the storage of tar and tar-products, cellars and tar pits were erected. Due to the operation of the plant, subsoil and groundwater were contaminated with tar-products. In the course of rehabilitation measures in the 1960-ies, approx. 8.000 litre creosote trickled into the ground during the removal of a vessel. In addition, it was found out, that the industrial well had been utilized for the absorption of overflowing tar-products and surface water. In 1990, tar was detected on the surface by the water surveillance authorities. -
Contaminated Site ST1 / Styria
Teerfabrik Lederer-Mellitzer
Subject of Project
On this areal in the community of Stocking, factory equipment for the production of tar-products was based after World War II. For the storage of tar and tar-products, cellars and tar pits were erected. Due to the operation of the plant, subsoil and groundwater were contaminated with tar-products. In the course of rehabilitation measures in the 1960-ies, approx. 8.000 litre creosote trickled into the ground during the removal of a vessel. In addition, it was found out, that the industrial well had been utilized for the absorption of overflowing tar-products and surface water. In 1990, tar was detected on the surface by the water surveillance authorities. -
Contaminated Site ST1 / Styria
Teerfabrik Lederer-Mellitzer
Subject of Project
On this areal in the community of Stocking, factory equipment for the production of tar-products was based after World War II. For the storage of tar and tar-products, cellars and tar pits were erected. Due to the operation of the plant, subsoil and groundwater were contaminated with tar-products. In the course of rehabilitation measures in the 1960-ies, approx. 8.000 litre creosote trickled into the ground during the removal of a vessel. In addition, it was found out, that the industrial well had been utilized for the absorption of overflowing tar-products and surface water. In 1990, tar was detected on the surface by the water surveillance authorities. -
Contaminated Site ST1 / Styria
Teerfabrik Lederer-Mellitzer
Subject of Project
On this areal in the community of Stocking, factory equipment for the production of tar-products was based after World War II. For the storage of tar and tar-products, cellars and tar pits were erected. Due to the operation of the plant, subsoil and groundwater were contaminated with tar-products. In the course of rehabilitation measures in the 1960-ies, approx. 8.000 litre creosote trickled into the ground during the removal of a vessel. In addition, it was found out, that the industrial well had been utilized for the absorption of overflowing tar-products and surface water. In 1990, tar was detected on the surface by the water surveillance authorities. -
Contaminated Site ST1 / Styria
Teerfabrik Lederer-Mellitzer
Subject of Project
On this areal in the community of Stocking, factory equipment for the production of tar-products was based after World War II. For the storage of tar and tar-products, cellars and tar pits were erected. Due to the operation of the plant, subsoil and groundwater were contaminated with tar-products. In the course of rehabilitation measures in the 1960-ies, approx. 8.000 litre creosote trickled into the ground during the removal of a vessel. In addition, it was found out, that the industrial well had been utilized for the absorption of overflowing tar-products and surface water. In 1990, tar was detected on the surface by the water surveillance authorities. -
Contaminated Site ST1 / Styria
Teerfabrik Lederer-Mellitzer
Subject of Project
On this areal in the community of Stocking, factory equipment for the production of tar-products was based after World War II. For the storage of tar and tar-products, cellars and tar pits were erected. Due to the operation of the plant, subsoil and groundwater were contaminated with tar-products. In the course of rehabilitation measures in the 1960-ies, approx. 8.000 litre creosote trickled into the ground during the removal of a vessel. In addition, it was found out, that the industrial well had been utilized for the absorption of overflowing tar-products and surface water. In 1990, tar was detected on the surface by the water surveillance authorities.
-
> more
Remediation measures:
- Exploration of subsoil / registration and demarcation of contaminated underground areas
- Pre-excavation in the non-saturated zone
- Demolition of former tar-pits and underground structures
- Excavation of the contaminated subsoil by means of large diameter drillings
- Cleaning of pumped out water
- Disposal of excavation and demolition materials
- Backfilling / Recultivation
Services provided by BALSA:
Complete realisation and carrying out of remediation measures:
- Basic engineering / planning of project-filing / detailed planning
- Design and carrying out of detailed exploration
- Engineering of remediation measures
- Carrying out of award procedures
- All agenda in connection with project-management and project-steering
Closure of the project: December 2012
-
Contaminated site N53 / Lower Austria
Teerfabrik Rütgers-Angern
Subject of Project
This old site is an area of around 11.2 hectares where a tar product company and a factory for the production of wood impregnation agents and a wood impregnation plant were operated between around 1860 and 1924. The soil is contaminated with polycyclic aromatic hydrocarbons in almost the entire area of the old site, and in some places there are even tar leaks on the surface.Based on the surface contamination, an extensive plum of BAK and BTEX and, to a lesser extent, heterocyclic aromatic and phenolic hydrocarbons and arsenic has formed in the groundwater. The outflowing pullutant loads are very high.
-
> more
Immediate Measures in accordance with § 30 Environmental Support Act:
Based on the results of soil analyses and the professional advice of the Federal Environmental Agency (Umweltbundesamt GmbH), the topsoil was exchanged in order to foreclose potential health risks. The essential element was the exchange of approx. 50 cm of the highly polluted topsoil in the area of approx. 48 plots of land (total area approx. 50.000 m²).
Assignments of BALSA:
Realisation of the project, acting as master of the works in substitution of the Austrian Federal Ministry of Agriculture, Forestry, Environment and Water Management:
- detailed planning
- carrying out of tendering and award procedures
- project-steering
- local technical and financial supervision of works
Finalization of immediate measures in accordance with §30 Environmental Support Act in May, 2015.